Individual Project Utilizing the Step-by-Step MRP Calculation Process, management homework help

Description

MGMT333 Unit 4 Reading: http://careered.libguides.com/aiu/mgmt333#s-lg-box-10117140750-1,000 Word White Paper; 1,200-1,500 words Utilizing
the Step-by-Step MRP Calculation Process, students will solve the
following MRP problem given: Product A is an end item and is made from
two units of B and four of C. B is made of three units of D and two of
E. Product C is made of two units of F and two of E. Product A has a
lead-time of one week. Products B, C and E have lead-times of two weeks.
Products D and F have a lead-time of three weeks. a. Show the bill of material (product structure tree). b.
If 100 units of A are required in week 10, develop the MRP planning
schedule, specifying when items are to be ordered and received. There
are currently no units of inventory on hand.

Leave a Comment